Installation of LLDPE (linear low density polyethylene) liner is largely complete in Phases 1, 2 and 3 of the capping works, with only extrusion welds on some of tthe panels remaining.

Completion of cap welding is expected early this week.

 

 

photo0583 1024x768

  photo0584 1024x768

An additional thirty shallow gas wells in Cell 3 have been installed to minimise surface emissions.  The connecion works were completed on 5 October and extraction fro the wells will be balanced during this week.

001 1 1024x768  001 9 1024x768

Drilling of additional deep gas well is scheduled to take place in approximately five weeks dependent on the weather. 

The Programme of Works will be concluded on completion of the drilling campaign in November.  Following the conclusion of the improvement programme, the actions will be reviewed and the site re-assessed for further works that can improve odour management.